All forms are in place on both Lot 2 and Lot 3 for pouring the foundation walls. I saw Paul, who said that they plan to pour TODAY at 1pm!
21 images 2. view towards Lot 2 4. Lot 2 5. Lot 2 6. Lot2 7. Lot 2 8. Lot 2 9. Lot 2 from the driveway - that foundation wall is going to be pretty tall 10. Entrance to Lot 3 11. Lot 3 12. Lot 3 14. Looking uphill at Lot 3 15. Uphill at Lot 3 16. Lot 3 17. view of Lot 7 (Rapp's) from the bench 18. Lot 7 - big footprint! Basement will be in the lowest area (crawl space on far side) 19. Lot 7 driveway 20. Lot 7 from wellhead 21. Probably ready for footers if it ever dries out. Paul said that they were ready to do the footers, when an inch of rain fell Saturday night. So they will be set back a while. |